青藏铁路的能源运输项目

类别:我们的业绩 发布日期:2012/3/23 浏览次数:1466

2009年9月永信达办理了地热管自南京至西藏格尔木的铁路运输。
客户由于经验不足包装设计全部按铁路平板车的宽度设计装载,该批货物在装运时,本着安全运输为原则,为客户节约物流费用为基石;与发运站的装卸、货调等相关部门不断协调装载加固方案,在原包装上采用错位式装载,最终由平板车改为铁路敞车装运。虽然装载加固难度增加了,由原来40分钟装载一车增加到2.5小时/车,但是为客户节省了总运价10%的加固费用。
Yongxinda transacted the rail way transport of terrestrial heat pipes from Nanjing to Golmud Tibet during Sep. 2009.
As the client have not enough experience of packing, Yongxinda need to repack all the cargos before loading considering of safety and cost saving. Yongxinda negotiated with correlative departments of dispatching station about reinforcing and dislocating the packing to change platforms to open-top wagons. Although it increased the difficulty of reinforcing loading and taking more time, it saved 10% of total freight for customer.